Tiler
Scope of Works — 32a Archbold Road, Roseville NSW 2069
13
Tasks
6
Rooms
3
Phases
0%
Complete
Phase Coverage
Pre-Con
Design
Approvals
Demo
Build
Finishes
External
Summary by Room
| Room | Tasks | Done | Phases |
|---|---|---|---|
| Kitchen | 3 | 0 | Pre-Con, Build |
| Ground Floor Bathroom | 3 | 0 | Pre-Con, Design |
| Upstairs Bathroom | 3 | 0 | Pre-Con, Design |
| Master Ensuite | 2 | 0 | Design, Build |
| Laundry | 1 | 0 | Build |
| Whole House | 1 | 0 | Design |
Detailed Scope
Kitchen
3 tasksPre-Construction Planning
Demolish existing kitchen (cabinetry, benchtops, splashback, appliances)
HighNot Started
REVISED: 16 general hrs + bin/equipment. Covers kitchen strip-out only.
Splashback supply & install (tile or stone)
LowNot Started
MILESTONE: Split into 2 sub-tasks.
Construction & Fitout
Kitchen — install splashback
MediumNot Started
Tiler to install between benchtop and overhead cabinets. Cut around power points. Grout and clean.
Ground Floor Bathroom
3 tasksPre-Construction Planning
GF Bathroom — strip-out (tiles, fittings, vanity, shower, WC)
HighIn Progress
QUOTED: A[price hidden] ex GST (A[price hidden] inc). 16 general hrs + bin + disposal.
GF Bathroom — wall & floor tiling
HighNot Started
~15m2 tile, [price hidden]-100/m2 tile + adhesive + grout. 4 days skilled tiler.
Design & Concept
GF Bathroom — select tiles (floor + wall + feature)
MediumNot Started
Style direction: classic with subtle pattern. Budget: [price hidden]-150/m² supply. Can match or complement FF Bathroom tiles. Floor: non-slip rating P3 minimum. Walls: white subway or large format. Suppliers: TileCloud, National Tiles, Academy Tiles.
Upstairs Bathroom
3 tasksPre-Construction Planning
FF Bathroom — strip-out & waste removal
HighIn Progress
QUOTED: A[price hidden] ex GST (A[price hidden] inc).
Scope of works
- 1Protect access route & staircase — Corflute/ram board to floors + stair treads; dust screens to doorways.
- 2Isolate & cap services — Water isolated at stop tap, circuits isolated at board before any removal.
- 3Remove all fittings, tiles & substrate — Strip to sound substrate — tiles, vanity, WC, bath, screen, tapware, sheeting where damaged.
- 4Cart away & skip hire — 4m³ skip incl. tipping; no rubble left on site overnight.
- 5Leave broom-clean & ready — Substrate swept, defects photographed, ready for rough-in inspection.
FF Bathroom — wall & floor tiling
HighNot Started
~18m2 tile (larger than GF due to bath). 5 days skilled tiler.
Scope of works
- 1Confirm set-out & tile layout with owner — Dry lay feature/niche; centre lines agreed; cuts kept to edges/inconspicuous.
- 2Full adhesive coverage — ≥90% coverage (95% wet areas), back-butter large format; no voids under tiles.
- 3Falls to waste maintained — Floor falls 1:80 even to waste; no ponding when tested.
- 4Mitred external corners — Mitred edges (no plastic trim) unless agreed; 2mm consistent joints.
- 5Grout, seal & silicone — Grout to spec; internal corners silicone (not grout); penetrations sealed.
Design & Concept
FF Bathroom — select tiles (floor + wall + feature)
MediumNot Started
Style direction: classic with feature wall. Budget: [price hidden]-150/m² supply. Floor: 300x300 or 600x600 porcelain. Walls: white subway or large format. Feature: marble-look or patterned encaustic. Suppliers: TileCloud, National Tiles, Academy Tiles. Get 3 samples of each.
Master Ensuite
2 tasksDesign & Concept
Master Ensuite — select tiles (floor + wall + feature)
MediumNot Started
Hero bathroom — premium tile selections. Budget: [price hidden]-250/m² supply. Consider: natural marble (Carrara, Calacatta), large format porcelain, or handmade zellige. Feature wall behind freestanding bath. Heated floor compatible.
Construction & Fitout
Master Ensuite — wall & floor tiling
HighNot Started
Laundry
1 tasksConstruction & Fitout
Laundry — tiling splashback + floor
MediumNot Started
Whole House
1 tasksDesign & Concept
Define hero materials palette (stone, timber species, metal finishes, tile families)
MediumNot Started
Max 3-4 hero materials that repeat throughout. Timber: oak vs walnut vs ash. Stone: marble vs engineered vs concrete. Metals: brass vs black vs brushed nickel.
Sequencing & Dependencies
Tasks that must be coordinated with other trades or completed in a specific order.
Demolish existing kitchen (cabinetry, benchtops, splashback, appliances)
Blocks
Splashback supply & install (tile or stone)
Depends on
Blocks
GF Bathroom — strip-out (tiles, fittings, vanity, shower, WC)
Blocks
GF Bathroom — wall & floor tiling
Depends on
Blocks
FF Bathroom — strip-out & waste removal
Blocks
FF Bathroom — wall & floor tiling
Depends on
Blocks
Master Ensuite — select tiles (floor + wall + feature)
Depends on
Blocks
FF Bathroom — select tiles (floor + wall + feature)
Depends on
Blocks
Master Ensuite — wall & floor tiling
Depends on
Blocks
GF Bathroom — select tiles (floor + wall + feature)
Depends on
Blocks