Owner

Scope of Works — 32a Archbold Road, Roseville NSW 2069

6

Tasks

1

Rooms

1

Phases

0%

Complete

Not Started: 6

Phase Coverage

Pre-Con

Design

Approvals

Demo

Build

Finishes

External

Summary by Room

RoomTasksDonePhases
Upstairs Bathroom60Pre-Con

Detailed Scope

Upstairs Bathroom

6 tasks

Pre-Construction Planning

FF Bathroom — strip-out, linings to studs, subfloor + GF ceiling (DIY)

High

Not Started

You + wife, 28 man-hrs (14h each). A[price hidden] skip bin. Now includes opening the GF ceiling for the WC waste re-route - hired labourers removed. Best done over the weekend before Day 1 so the trade programme still starts Monday.

1 lotUpstairs BathroomPre-Construction Planning

FF Bathroom — paint GF ceiling below

High

Not Started

DIY - 2 man-hrs. Paint only. PARALLEL - downstairs.

1 lotUpstairs BathroomPre-Construction Planning

FF Bathroom — paint ceiling, 2 coats

High

Not Started

DIY - 5 man-hrs, 2 coats. Evening, after the 3rd membrane coat cures. Paint only.

1 lotUpstairs BathroomPre-Construction Planning

FF Bathroom — paint walls above the tile line, 2 coats

High

Not Started

DIY - 7 man-hrs, 2 coats over ~33 m2 above the tile line. Paint only.

1 lotUpstairs BathroomPre-Construction Planning

FF Bathroom — paint touch-up

High

Not Started

DIY - 2 man-hrs touch-up.

2 hrUpstairs BathroomPre-Construction Planning

FF Bathroom — snagging, defects, compliance pack

High

Not Started

DIY. Compliance pack: plumbing Certificate of Compliance, waterproofing certificate, electrical CCEW, marked-up as-built.

6 hrUpstairs BathroomPre-Construction Planning