← All tradesPrint / PDF

General

Scope of Works — 32a Archbold Road, Roseville NSW 2069

139

Tasks

19

Rooms

7

Phases

0%

Complete

Not Started: 139

Phase Coverage

Pre-Con

Design

Approvals

Demo

Build

Finishes

External

Summary by Room

RoomTasksDonePhases
Whole House280Design, Approvals
Other260Design, Approvals, Demo, Build
Lounge130Design, Build, Finishes
Driveway Wall & New Staircase110Design, Approvals, Finishes
Driveway & Ramp100Pre-Con, Build, Finishes
Facade90Design, Build, Finishes
Dining90Design, Build, Finishes
Upstairs Bathroom80Pre-Con, Design
Master Ensuite60Design, Build, Finishes
Kitchen50Pre-Con, Design, Build, Finishes
Ground Floor Bathroom40Pre-Con, Build
Bedroom 220Build, Finishes
Master Suite20Build, Finishes
Laundry10Finishes
Study10Finishes
Library Shelves10Design
Foyer10Finishes
Landscaping10External
Bedroom 310Finishes

Detailed Scope

Whole House

28 tasks

Design & Concept

Run brief through Maket.ai or ArkDesign.ai for floor plan candidates

Medium

Not Started

Feed in sqm, bed/bath, orientation, key rooms. Generate dozens of variations. Pick 2-3 candidates and refine with prompts like 'move master to rear' or 'increase kitchen by 15%'.

No direct cost — planning/decision task. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Whole HouseDesign & Concept

[Stage 2] Set up partner login with row-level security (hide costs)

High

Not Started

Scoped Supabase RLS so wife sees: rooms, panoramas, finishes (product_name, preview_image, status), comments (read/write own). Hidden from wife: cost on finishes and decisions, supplier financial detail, full decision rationale (show summary only). Test thoroughly before sharing access.

Owner labour — no direct cost. Time investment only. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Whole HouseDesign & Concept

Import 3D model into Twinmotion and iterate finishes

Medium

Not Started

Free for personal use. Walk through in real time, swap cladding/windows/floors, drop in furniture, change time of day and weather. Export stills of key views.

No direct cost — planning/decision task. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Whole HouseDesign & Concept

Scan existing house with Polycam or Luma AI

High

Not Started

Capture exterior (all 4 elevations), key interior rooms, site boundaries. Photograph everything: street view, neighbouring houses for heritage context, garden, internal rooms. This becomes the 'before' baseline and constraint set.

Owner labour — no direct cost. Time investment only. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Whole HouseDesign & Concept

Flow analysis — movement patterns through the house

Medium

Not Started

Map daily routines: wake up → bathroom → kitchen → car. Entertaining flow: entry → kitchen → dining → outdoor. Laundry circuit. Kids vs adults zones.

No direct cost — planning/decision task. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Whole HouseDesign & Concept

[Stage 2] Mobile UX polish and partner walkthrough test

Medium

Not Started

Test on her actual phone (not desktop preview). Check: panorama load speed on 4G, touch gestures feel right, comment flow is obvious, finish hotspots are tappable not fiddly, navigation between rooms is intuitive. Iterate based on her feedback before considering Stage 2 done.

Owner labour — no direct cost. Time investment only. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Whole HouseDesign & Concept

Visit 3-5 renovated homes in Ku-ring-gai for inspiration

Low

Not Started

Open homes, completed projects by shortlisted architects. Take photos, note finishes, ask about costs and timeframes. Roseville, Lindfield, Killara.

Owner labour — no direct cost. Time investment only. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Whole HouseDesign & Concept

Create mood boards per room (Kitchen, Lounge, Bathrooms, Master Suite, Facade)

High

Not Started

Collect Instagram, Pinterest, magazine references. Organise by room. Include textures, colours, materials, spatial feel. Nancy to co-create.

Owner labour — no direct cost. Time investment only. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Whole HouseDesign & Concept

Select interior colour palette (walls, trim, ceilings, feature walls)

Medium

Not Started

Warm neutrals base, consider flow between rooms. Accent colours for bathrooms. Ceiling colour strategy (white vs tinted).

Owner labour — no direct cost. Time investment only. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Whole HouseDesign & Concept

Floor plan options evaluation (compare 2-3 layouts)

High

Not Started

Score each option: room sizes, flow, natural light, buildability, cost, compliance. Decision matrix with Nancy. Select preferred and brief architect for development.

No direct cost — planning/decision task. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Whole HouseDesign & Concept

[Stage 2] Add rooms, finishes, comments tables to Supabase schema

High

Not Started

Add to migration file 001 before running. Tables: rooms (id, name, floor, area_sqm, stage_id fk, description, panorama_url, model_node_name), finishes (id, room_id fk, category, product_name, supplier_stakeholder_id fk, cost, document_id fk, status, preview_image_url), comments (id, room_id fk OR finish_id fk, author, body, created_at, resolved).

Owner labour — no direct cost. Time investment only. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Whole HouseDesign & Concept

[Stage 2] Choose 360 tour platform (Kuula vs Pano2VR vs custom Pannellum)

MediumDecision needed

Not Started

Options: (a) Kuula — ~[price hidden]/month, easiest, embeds via iframe, hotspot editor included; (b) Pano2VR — one-time license, full control, self-hosted; (c) Custom build with Pannellum or Marzipano (open source JS libs) — most integrated with Renokit but requires dev work. Recommend Kuula for Stage 2 MVP, revisit custom for Stage 3.

Owner labour — no direct cost. Time investment only. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Whole HouseDesign & Concept

[Stage 2] Build 360 tour with room hotspots and inter-room navigation

Medium

Not Started

Build navigable tour: floor plan landing page with clickable room hotspots, each loads the room's 360 view, arrows between connected rooms (kitchen → dining → living etc.), info hotspots on key finishes within each panorama. Export embed code for Renokit.

Owner labour — no direct cost. Time investment only. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Whole HouseDesign & Concept

Rebuild chosen floor plan as 3D model

Medium

Not Started

Options: (a) SketchUp Free manually — weekend job, full control; (b) Maket/Finch auto-extrude — faster, less control; (c) Hire Upwork freelancer [price hidden]-500 for clean SketchUp/Revit model in a week. Freelancer likely best ROI.

No direct cost — planning/decision task. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Whole HouseDesign & Concept

Fixtures schedule — specify every tap, handle, switch, hinge

Medium

Not Started

Spreadsheet of every fixture: product, supplier, cost, lead time. Consistent finish family throughout (e.g., all brushed brass). Include backups for discontinued items.

No direct cost — planning/decision task. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Whole HouseDesign & Concept

Storage audit — inventory current + plan future storage needs

Low

Not Started

Linen, pantry, wardrobe, garage, workshop, outdoor. What are you storing now that you shouldn't be? Built-in vs freestanding.

No direct cost — planning/decision task. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Whole HouseDesign & Concept

Generate cinematic walkthrough video for wife view

Medium

Not Started

Export Twinmotion video directly, OR feed key frames into Sora/Runway for smooth cinematic camera moves. This is the highest-leverage stakeholder alignment artefact.

Owner labour — no direct cost. Time investment only. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Whole HouseDesign & Concept

[Stage 2] Brief 3D model freelancer on web-export hygiene requirements

High

Not Started

Brief freelancer that the 3D model must be web-export ready: clean topology, parent objects named per room (Kitchen, Living, Master, etc.), finishes as separate assignable material layers grouped by category (Floors, Walls, Joinery, Fixtures, Lighting), scale in metres, sensible origin. The model_node_name in the rooms table must match the parent object names exactly.

Owner labour — no direct cost. Time investment only. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Whole HouseDesign & Concept

[Stage 2] Build Renokit /house route with floor plan landing and dynamic room pages

Medium

Not Started

Renokit page structure: /house route shows floor plan, /house/[room] loads tour for that room, sidebar pulls live data from Supabase showing finishes, decisions, and recent comments for that room. Use Next.js dynamic routes and Supabase client SDK.

Owner labour — no direct cost. Time investment only. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Whole HouseDesign & Concept

[Stage 2] Upload panoramas to Supabase Storage and link in rooms table

Medium

Not Started

Upload all panoramas to Supabase Storage bucket reno-docs under /panoramas/ path. Update rooms table panorama_url field with storage paths. Keep originals locally as backup.

Owner labour — no direct cost. Time investment only. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Whole HouseDesign & Concept

[Stage 2] Wire finish hotspots to Supabase finishes/decisions/documents tables

High

Not Started

Each finish hotspot in the panorama links to a finishes table row. On click, surface: product name, supplier, cost, spec sheet (from documents table), status, decision rationale (from decisions table). This is the moment the tour stops being decoration and becomes a live design document.

Owner labour — no direct cost. Time investment only. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Whole HouseDesign & Concept

Migrate Roseville reno backend from Notion to Supabase

High

Not Started

Implement via Claude Code. Build order: 1) Supabase project + auth setup; 2) Schema migrations (stages, stakeholders, trades, bids, budget_lines, expenses, risks, decisions, documents, updates); 3) Indexes + generated columns; 4) CSV export from Notion → seed scripts; 5) RLS policies (scope partner view, hide sensitive cost fields); 6) Pre-built views: v_budget_summary, v_active_bids, v_top_risks, v_cashflow_monthly; 7) Supabase Storage bucket (reno-docs) for documents; 8) Point Vercel front end at Supabase; 9) Build add/edit forms early for bids, decisions, expenses, updates; 10) Wire MCP so AJ can query Postgres directly for analysis.

Owner labour — no direct cost. Time investment only. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Whole HouseDesign & Concept

Generate 50 concept images in Midjourney/Krea

Medium

Not Started

Build mood board: exterior Georgian variations, then interiors room by room (kitchen, living, master, bathrooms). Iterate one variable per prompt. Save the resonant ones.

Owner labour — no direct cost. Time investment only. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Whole HouseDesign & Concept

Room-by-room functional brief (how each space is used, by whom, when)

High

Not Started

Workshop with Nancy. Morning routine flow, entertaining scenarios, WFH needs, kids homework zone, storage requirements per room. This drives the spatial design.

No direct cost — planning/decision task. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Whole HouseDesign & Concept

Natural light mapping — sun study per room (orientation, time of day)

Low

Not Started

North-facing rooms = living areas. Window sizing, skylights, light wells. Afternoon western sun management. Inform window and room placement decisions.

No direct cost — planning/decision task. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Whole HouseDesign & Concept

[Stage 2] Build comment overlay on panoramas writing to comments table

High

Not Started

On any panorama or finish, wife can leave a comment that writes to the comments table. Threaded view per room. Mark as resolved when addressed. Email/push notification on new comments (optional, Stage 2.5). This is the killer feature — design feedback in context, not over text messages.

Owner labour — no direct cost. Time investment only. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Whole HouseDesign & Concept

Polish key Twinmotion stills in Krea/Midjourney

Medium

Not Started

Take Twinmotion screenshots, drop into Krea with prompts for golden hour, established garden, photoreal styling. Preserves geometry but elevates render quality.

Owner labour — no direct cost. Time investment only. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Whole HouseDesign & Concept

Planning & Approvals

Pull Ku-ring-gai heritage DCP and read relevant sections

High

Not Started

Heritage conservation overlay will constrain exterior options. Read before falling in love with a design that won't get DA approval.

Owner labour — no direct cost. Time investment only. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Whole HousePlanning & Approvals

Other

26 tasks

Design & Concept

Create concept image pack (Georgian + modern references)

Urgent

Not Started

Use Midjourney / DALL-E — bring to architect briefings to reduce design hours

Owner labour — no direct cost. Time investment only. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Design & Concept

Create mood board (materials, finishes, fixtures)

Medium

Not Started

Focus on Georgian character elements — stone, columns, sash windows, symmetry

Owner labour — no direct cost. Time investment only. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Design & Concept

Pull existing floor plan + site plan from realestate.com.au

High

Not Started

Download the floor plan and site plan from the original listing on realestate.com.au or domain.com.au. Save as high-res images. These become the base for briefing the architect and kitchen designer.

Owner labour — no direct cost. Time investment only. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Design & Concept

Planning & Approvals

Issue tender RFQ to 3-4 shortlisted builders

Medium

Not Started

Send formal Request for Quote to shortlisted builders. Include: full drawing set, specifications, scope of works schedule, timeline requirements, insurances required, contract type (HIA or custom). Allow 3-4 weeks for responses.

Owner labour — no direct cost. May trigger professional fees tracked separately. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Planning & Approvals

Draft builder tender scope of works template

High

Not Started

Detailed scope = more comparable bids, less variation risk

Owner labour — no direct cost. Time investment only. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Planning & Approvals

Define garage scope (single / double, internal access, EV charging)

High

Not Started

Check if garage needs separate DA or can be included in main DA

Owner labour — no direct cost. Time investment only. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Planning & Approvals

Set up weekly site inspection cadence

Low

Not Started

During construction: visit site weekly (same day/time). Bring: hard hat, steel-caps, camera/phone, checklist. Check: progress vs program, quality of work, safety compliance, material storage. Document with photos and send builder a summary email.

Owner labour — no direct cost. Time investment only. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Planning & Approvals

Develop construction program / critical path schedule

Medium

Not Started

Design → DA → tender → construction → fit-out → landscaping

Owner labour — no direct cost. May trigger professional fees tracked separately. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Planning & Approvals

Review Ku-ring-gai LEP & DCP controls for Roseville

High

Not Started

Check heritage overlay, FSR, height limits, setbacks

Owner labour — no direct cost. Time investment only. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Planning & Approvals

Longlist 6-8 builders for tender

Medium

Not Started

Target builders with Georgian/heritage residential experience in Upper North Shore

Owner labour — no direct cost. May trigger professional fees tracked separately. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Planning & Approvals

Negotiate and award building contract

Low

Not Started

Review all tender responses. Negotiate: price, payment schedule (progress claims vs fixed), provisional sums, timeline with liquidated damages, defects liability period (min 6 months), insurances (Home Building Compensation Fund). Use HIA contract or equivalent.

Owner labour — no direct cost. May trigger professional fees tracked separately. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Planning & Approvals

Decide: live in during works or relocate

High

Not Started

Structural + double-storey addition will be very disruptive — plan relocation if feasible

Owner labour — no direct cost. Time investment only. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Planning & Approvals

Draft desired floor plan (rooms, layout, sqm targets)

Urgent

Not Started

Use Planner 5D or RoomSketcher — have a clear layout before architect briefing

Owner labour — no direct cost. Time investment only. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Planning & Approvals

Set up project budget tracker (by workstream)

Urgent

Not Started

Sub-[price hidden] AUD all-in — QS feasibility plan to validate this

Owner labour — no direct cost. Time investment only. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Planning & Approvals

Build bid comparables sheet (apples-to-apples comparison)

Medium

Not Started

Create a spreadsheet comparing builder quotes line-by-line. Columns: item, Builder A price, Builder B price, Builder C price, notes. Normalise inclusions/exclusions so quotes are comparable. Flag any provisional sums or allowances.

Owner labour — no direct cost. May trigger professional fees tracked separately. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Planning & Approvals

Confirm financing structure (cash / mortgage / construction loan)

High

Not Started

Meet with mortgage broker to confirm: (1) How much equity available for redraw, (2) Construction loan terms and draw-down schedule, (3) Cash reserves needed for deposits and progress payments. Target: total funding of [price hidden].

Owner labour — no direct cost. Time investment only. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Planning & Approvals

Define must-haves vs nice-to-haves for scope

High

Not Started

List every scope item and classify as Must-Have (non-negotiable), Nice-to-Have (if budget allows), or Future (defer to later stage). Key must-haves: kitchen, bathrooms, facade. Key nice-to-haves: underground garage, pool, landscaping.

Owner labour — no direct cost. Time investment only. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Planning & Approvals

Demolition & Strip-out

Extension — site set-out and temporary fencing

High

Not Started

Surveyor marks building lines. Hoarding and safety fencing around demolition zone. Notify neighbours.

Demolition & Strip-out

Extension — demolish existing front wall section

High

Not Started

Remove existing front facade wall to connect new extension. Temporary weatherproofing. Structural propping as per engineer's spec.

Demolition & Strip-out

Construction & Fitout

Extension — first floor timber frame and bearers (63m²)

High

Not Started

Timber frame walls, bearers and joists for first floor. Tie into existing roof structure. Structural engineer inspections at each stage.

Construction & Fitout

Post-extension — internal fit-out (lounge, Bed 4, master suite, ensuite)

Low

Not Started

MILESTONE: Now tracked via 5 sub-tasks (lounge, bed 4, master suite, ensuite plumbing, first floor electrical). Check sub-tasks for progress.

No direct cost — planning/decision task. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Construction & Fitout

Underground garage — tanked waterproofing membrane

High

Not Started

Full tanked waterproofing to walls, floor and roof slab. Critical for below-ground structure. Use torch-on membrane or spray-applied system. 10-year warranty minimum.

Construction & Fitout

Underground garage — excavation and rock breaking

High

Not Started

Cut into hillside from driveway side. 5m natural slope means mostly horizontal cut, not dig-down. Allow for rock hammering on Roseville ridge. Spoil removal off-site.

Construction & Fitout

Extension — roof framing and tie-in to existing

High

Not Started

New roof structure over extension. Match existing roof pitch and material. Flash and weatherseal at junction with existing roof.

Construction & Fitout

Post-extension — extension structure (footings, slab, frame)

Low

Not Started

MILESTONE: This task is now tracked via 6 sub-tasks (site set-out, demolish, footings, slab, frame, roof). Check sub-tasks for progress.

No direct cost — planning/decision task. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Construction & Fitout

Post-extension — Georgian front facade + portico + windows

Low

Not Started

MILESTONE: Now tracked via 5 sub-tasks (brickwork/render, portico, windows, mouldings, front door). Check sub-tasks for progress.

No direct cost — planning/decision task. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Construction & Fitout

Lounge

13 tasks

Design & Concept

Lounge — design brief and layout planning

Medium

Not Started

Define lounge layout: furniture placement, TV/media wall, fireplace focal point, window seat. Open plan connection to kitchen/dining.

LoungeDesign & Concept

Lounge — select wall paint colour

Medium

Not Started

Georgian palette: warm whites, soft greys, or heritage colours. Test 3 sample pots on wall.

LoungeDesign & Concept

Lounge — select chandelier or pendant

Medium

Not Started

Statement chandelier for formal lounge. Consider: scale to room height, dimmer compatibility. Budget: A[price hidden]-2,000.

LoungeDesign & Concept

Lounge — select Georgian trim profile

Medium

Not Started

Choose cornice, skirting, architrave, and wainscoting profiles. Visit Intrim Mouldings or similar.

LoungeDesign & Concept

Lounge — select curtains or shutters

Medium

Not Started

Plantation shutters (Georgian authentic) or floor-length curtains (more luxe). Get quotes for both.

LoungeDesign & Concept

Lounge — select flooring type and colour

Medium

Not Started

Decision: sand and polish existing timber, or new engineered timber? Match or complement kitchen flooring. Get 3 samples.

LoungeDesign & Concept

Construction & Fitout

Lounge — procure chandelier

Medium

Not Started

Order selected chandelier. Confirm ceiling box can support weight. Check lead time.

LoungeConstruction & Fitout

Lounge — procure curtains or shutters

Medium

Not Started

Order from selected supplier. Measure-to-install service preferred.

LoungeConstruction & Fitout

Extension fit-out — grand lounge framing, insulation and plasterboard

High

Not Started

Extended lounge ~65m². Frame internal walls, insulate external walls, plasterboard and set. Ready for cornices and paint.

LoungeConstruction & Fitout

Finishes

Lounge — fireplace restoration (clean, re-point, mantel)

Medium

Not Started

Clean firebox, re-point mortar joints, restore/replace mantelpiece, paint surround. Specialist 2 days. CONFIDENCE: 45/100 — Benchmark estimate based on Sydney 2026 renovation rates. No quote obtained yet. QUESTIONS: (1) Has this been quoted by a supplier/contractor? (2) Are material selections confirmed? (3) Any site-specific factors that could affect cost?
2 dayLoungeFinishes

Lounge — Georgian trim (cornices, skirting, architraves, wainscoting)

High

Not Started

Hero room — detail level drives resale

Georgian decorative mouldings throughout lounge: Cornices: ~28 LM perimeter (7m x 4 walls) x [price hidden]/LM (140mm profile, supply + fix + paint) = [price hidden]. Skirting: ~28 LM x [price hidden]/LM (185mm profile, MDF, supply + fix + paint) = [price hidden]. Architraves: 3 door openings x ~5 LM each = 15 LM x [price hidden]/LM = [price hidden]. Wainscoting/panelling: allowance for 1 feature wall (~8 sqm) = [price hidden]. Total: cornices [price hidden] + skirting [price hidden] + architraves [price hidden] + wainscoting [price hidden] = [price hidden] ≈ [price hidden]. CONFIDENCE: 50/100 — Profile selection not confirmed. Room perimeter estimated. Heritage-appropriate profiles available from Intrim Group. If full-room wainscoting wanted (all 4 walls), add [price hidden]-3K. QUESTIONS: (1) Cornice profile — which Georgian profile? (egg & dart, dentil, plain cove?). (2) Skirting height — 135mm or 185mm? (3) Wainscoting — one feature wall or all walls? (4) Chair rail height — 900mm or 1000mm? (5) MDF or plaster for cornices?
64 lmLoungeFinishes

Lounge — snagging

Low

Not Started

Allowance for 4-8 hours defect rectification @ [price hidden]/hr trade rate + materials. CONFIDENCE: 65/100 — Allowance-based. Actual snagging depends on quality of preceding trades. QUESTIONS: (1) Is this a builder responsibility under contract (defects liability period)? (2) Or a separate engagement for independent snagging inspector?
6 hrLoungeFinishes

Lounge — protect open fireplace during works

High

Not Started

Fireplace is a retained feature

Allowance based on Sydney 2026 renovation benchmarks. Verify with supplier quote. CONFIDENCE: 45/100 — Benchmark estimate based on Sydney 2026 renovation rates. No quote obtained yet. QUESTIONS: (1) Has this been quoted by a supplier/contractor? (2) Are material selections confirmed? (3) Any site-specific factors that could affect cost?
1 lotLoungeFinishes

Driveway Wall & New Staircase

11 tasks

Design & Concept

LiDAR scan hillside area to collect measurements

Urgent

Not Started

Owner task. Use iPhone Pro LiDAR scanner via Polycam or 3D Scanner app. Capture: existing retaining wall height and condition, slope gradient, staircase location, driveway edge, trees/vegetation. Export as .obj or .las for architect/engineer.

Driveway Wall & New StaircaseDesign & Concept

Research retaining wall material options and costs

High

Not Started

Owner task. Create comparison matrix: material, cost/m², structural capacity, drainage requirements, aesthetic, maintenance, lifespan. Shortlist 2-3 for structural engineer to assess feasibility.

Driveway Wall & New StaircaseDesign & Concept

Photograph existing retaining wall and staircase from all angles

Urgent

Not Started

Owner task. Take photos of: wall face (both sides if accessible), top and base, any cracks or bulging, existing drainage, staircase condition, handrail, vegetation growing into wall. Annotate with measurements.

Driveway Wall & New StaircaseDesign & Concept

Research staircase material and design options

High

Not Started

Owner task. Key considerations: number of treads (calculate from LiDAR height data), landing every 18 risers (code), handrail style, step lighting, non-slip surface, drainage at base. Width: minimum 900mm.

Driveway Wall & New StaircaseDesign & Concept

Generate concept images for new retaining wall and staircase

High

Not Started

Owner task. Generate 5-10 concept renders showing: architectural stone-faced retaining wall, integrated concrete staircase with LED step lights, handrail options (steel/glass/timber), planting pockets, and how it connects to the driveway and rear yard.

Driveway Wall & New StaircaseDesign & Concept

Define scope brief for retaining wall and staircase project

High

Not Started

Owner task. One-page brief covering: existing conditions (from LiDAR + photos), desired outcome, material preference, parking area dimensions, staircase width and landing positions, drainage strategy, lighting requirements, timeline constraints.

Driveway Wall & New StaircaseDesign & Concept

Planning & Approvals

Check if council approval required for retaining wall height

High

Not Started

Owner task. Check Ku-ring-gai DCP for retaining wall controls. Walls over 600mm exposed height typically need council approval. May require: development consent, neighbour notification, engineer certification. Ask town planner for advice.

Driveway Wall & New StaircasePlanning & Approvals

Get 3 quotes from retaining wall contractors

High

Not Started

Owner task. Provide each contractor with: structural engineer drawings, geotech report, scope brief, concept images. Quote to include: excavation, wall construction, drainage, staircase, handrail, backfill. Allow 2-3 weeks for responses.

Driveway Wall & New StaircasePlanning & Approvals

Award retaining wall contractor

Medium

Not Started

Owner task. Compare: total price, timeline, inclusions/exclusions, payment schedule, insurance, warranty. Check contractor's license, insurance, and 2-3 recent references. Sign contract before any work starts.

Driveway Wall & New StaircasePlanning & Approvals

Finishes

Snagging and defects inspection — retaining wall and staircase

Medium

Not Started

Owner + contractor walkthrough. Check: wall plumb and level, drainage working (test with hose), stair treads level, handrail secure, finish quality, no cracks, lighting working. Mark defects with tape for rectification.

Driveway Wall & New StaircaseFinishes

Apply finish to retaining wall face

Medium

Not Started

Final wall finish per material selection: cement render + paint, stone cladding (natural or manufactured), textured coating, or exposed concrete with form liner texture. Seal/waterproof external face.

Driveway Wall & New StaircaseFinishes

Driveway & Ramp

10 tasks

Pre-Construction Planning

Chicken-wire the lower fence so Apollo can't get out

High

Not Started

Dog-proof the lower fence line with chicken wire — do this early so Apollo is secure once demolition starts.

Driveway & RampPre-Construction Planning

Buy chicken wire, star pickets & fixings

High

Not Started

Already have the wire & fixings
Driveway & RampPre-Construction Planning

Run & fix wire along the lower fence line

High

Not Started

DIY install
Driveway & RampPre-Construction Planning

Verify concrete recycling + RCA sub-base is viable & economic

High

Not Started

Call concrete recyclers (e.g. Kimbriki, Benedict, Bingo): confirm they take clean concrete, get per-tonne tip rate + RCA road-base buy-back price. Compare "recycle & rebuy" vs landfill + imported road base. PRECONDITION: asbestos check on the (pre-1990?) garage/slab before any crush/recycle; strip reo, keep concrete clean.

Driveway & RampPre-Construction Planning

Construction & Fitout

Replace the driveway gate

Medium

Not Started

Old gate comes off during the garage demolition; install the new gate once works are complete.

Driveway & RampConstruction & Fitout

Supply new gate

Medium

Not Started

Driveway & RampConstruction & Fitout

Install gate, posts & hardware

Medium

Not Started

Driveway & RampConstruction & Fitout

Finishes

Reseal the cobblestone driveway

Medium

Not Started

Seal cobblestones and joints once laid and cured.

Driveway & RampFinishes

Supply sealer

Medium

Not Started

Driveway & RampFinishes

Apply sealer coats

Medium

Not Started

107.4 m² measured area
107.4 Driveway & RampFinishes

Facade

9 tasks

Design & Concept

Facade — design brief for Georgian character

Medium

Not Started

Define: symmetry, window proportions, render vs brick, column style, portico, colour palette. Reference concept pack.

FacadeDesign & Concept

Heritage & streetscape assessment (Ku-ring-gai council character requirements)

High

Not Started

Check if property is in a heritage conservation area. Review DCP character provisions. Photograph neighbouring properties. Understand council expectations for street-facing design.

No direct cost — planning/decision task. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
FacadeDesign & Concept

Construction & Fitout

Facade — portico columns and entablature construction

High

Not Started

Central entry portico with classical columns. Timber or rendered masonry columns. Entablature, cornice moulding. This is the centrepiece of the facade.

FacadeConstruction & Fitout

Facade — decorative mouldings, keystones and quoins

High

Not Started

Georgian decorative elements: window keystones, corner quoins, string course between floors. Can be precast concrete, GRC, or rendered.

FacadeConstruction & Fitout

Facade — procure front door

Medium

Not Started

Order Georgian panelled front door with sidelights. Confirm dimensions, hardware (brass), colour.

FacadeConstruction & Fitout

Facade — procure windows

Medium

Not Started

Order Georgian sash windows per selection. Sizes from architect drawings. Timber sash lead time 8-12 weeks.

FacadeConstruction & Fitout

Facade — brickwork or render to new extension walls

High

Not Started

Two-storey Georgian facade, 10.5m wide. Full brick or cement render depending on design. Must match proportions and style of period Georgian homes.

FacadeConstruction & Fitout

Facade — front door and sidelights

High

Not Started

Georgian panelled front door with sidelights and fanlight. Solid timber, painted. Hardware: brass lever set, knocker. Must suit portico proportions.

FacadeConstruction & Fitout

Finishes

Facade — snagging & defects

Low

Not Started

Allowance for 4-8 hours defect rectification @ [price hidden]/hr trade rate + materials. CONFIDENCE: 65/100 — Allowance-based. Actual snagging depends on quality of preceding trades. QUESTIONS: (1) Is this a builder responsibility under contract (defects liability period)? (2) Or a separate engagement for independent snagging inspector?
6 hrFacadeFinishes

Dining

9 tasks

Design & Concept

Dining — select wall treatment

Medium

Not Started

Wainscoting/panelling for Georgian detail, or plain painted walls? Feature wall?

DiningDesign & Concept

Dining — design brief and layout

Medium

Not Started

Define dining layout: table size, pendant position, connection to kitchen island. Open plan flow.

DiningDesign & Concept

Dining — select paint colour

Medium

Not Started

Coordinate with lounge and kitchen. Same colour throughout open plan, or accent wall?

DiningDesign & Concept

Dining — select flooring

Medium

Not Started

Must be continuous with kitchen. Engineered timber preferred for open plan consistency.

DiningDesign & Concept

Dining — select pendant light

Medium

Not Started

Pendant over dining table. Height 700-800mm above table. Style match with kitchen pendants. Budget: A[price hidden]-1,000.

DiningDesign & Concept

Construction & Fitout

Dining — procure pendant light

Medium

Not Started

Order selected pendant. Confirm ceiling point position with electrician.

DiningConstruction & Fitout

Finishes

Dining — snagging

Low

Not Started

Allowance for 4-8 hours defect rectification @ [price hidden]/hr trade rate + materials. CONFIDENCE: 65/100 — Allowance-based. Actual snagging depends on quality of preceding trades. QUESTIONS: (1) Is this a builder responsibility under contract (defects liability period)? (2) Or a separate engagement for independent snagging inspector?
6 hrDiningFinishes

Dining — cornice/ceiling detail restoration or new Georgian trim

Medium

Not Started

~16 LM Georgian profile cornice. MDF/plaster [price hidden]/lm supply + install [price hidden]/lm + paint. CONFIDENCE: 45/100 — Benchmark estimate based on Sydney 2026 renovation rates. No quote obtained yet. QUESTIONS: (1) Has this been quoted by a supplier/contractor? (2) Are material selections confirmed? (3) Any site-specific factors that could affect cost?
16 lmDiningFinishes

Dining — wall treatment (wainscoting / panelling if Georgian detail)

Medium

Not Started

~12 sqm MDF panelling. Supply [price hidden]/sqm (routed panels + rails) + install [price hidden]/sqm + paint 2 coats. CONFIDENCE: 45/100 — Benchmark estimate based on Sydney 2026 renovation rates. No quote obtained yet. QUESTIONS: (1) Has this been quoted by a supplier/contractor? (2) Are material selections confirmed? (3) Any site-specific factors that could affect cost?
12 sqmDiningFinishes

Upstairs Bathroom

8 tasks

Pre-Construction Planning

FF Bathroom — site verification (measure, subfloor, stack, wiring, duct route)

High

Not Started

Confirm: (1) timber subfloor vs concrete slab — drives plumbing rough-in cost (currently only 50/100 confidence); (2) distance from soil stack to WC/shower; (3) existing wiring reusable or full rewire; (4) exhaust fan duct route to outside; (5) exact tiled area vs the 48 sqm / 23 sqm waterproofing assumptions (room scanned at 2.41 x 3.03 m = 6.9 sqm, L-shaped).

Upstairs BathroomPre-Construction Planning

FF Bathroom — lock fixture & finish selections

HighDecision needed

Not Started

Decide: tile format + $/sqm budget; tapware finish + brand tier (Caroma/Phoenix mid vs Brodware premium); vanity width + wall-hung vs floor-standing; WC style; rain-only vs rain+hand shower. Georgian Spa design references in the floorplans PDF. Feeds the procurement Bill of Materials.

Upstairs BathroomPre-Construction Planning

FF Bathroom — prepare tender scope pack

High

Not Started

Include: scanned room plan + Georgian Spa 3D/tile setout, NE recess shower detail (0.95 x 0.95 m frameless, NCC 2022 / AS 3740 falls + stepdown), fixture schedule, tile schedule with formats, waterproofing membrane system (pick Ardex/Laticrete/Mapei). Publish via the /tender/[trade] pages.

Upstairs BathroomPre-Construction Planning

FF Bathroom — shortlist wet trades (plumber, tiler/waterproofer, electrician, glazier)

High

Not Started

Target 3 candidates per trade. Add each via the room contractors panel. Ask tilers whether they include their own demo and waterproofing (many do — collapses 3 line items into one quote).

Upstairs BathroomPre-Construction Planning

FF Bathroom — collect & compare quotes vs estimates

Medium

Not Started

Estimates to beat: plumbing rough-in [price hidden] electrical [price hidden] waterproofing [price hidden] tiling [price hidden] shower screen [price hidden] strip-out [price hidden]. Flag anything >15% over.

Upstairs BathroomPre-Construction Planning

FF Bathroom — decide: split trades vs single bathroom renovator

MediumDecision needed

Not Started

Get at least one whole-job quote alongside split-trade quotes to price the coordination premium explicitly.

Upstairs BathroomPre-Construction Planning

FF Bathroom — snagging & defects

Medium

Not Started

Final walk-through punch list. Caulk touch-ups, silicon, fitting adjustments. Matches GF spec.

Allowance for 4-8 hours defect rectification @ [price hidden]/hr trade rate + materials. CONFIDENCE: 65/100 — Allowance-based. Actual snagging depends on quality of preceding trades. QUESTIONS: (1) Is this a builder responsibility under contract (defects liability period)? (2) Or a separate engagement for independent snagging inspector?

Scope of works

  1. 1
    Full defect inspectionWalk-through against scope; list any defects with photos.
  2. 2
    Rectify & sign offAll defects rectified; final clean; owner sign-off.
6 hrUpstairs BathroomPre-Construction Planning

Design & Concept

FF Bathroom — design brief and layout

Medium

Not Started

Layout: shower position, vanity size (900 or 1200), bath (freestanding or built-in), WC position. Plumber to confirm waste/supply feasibility.

Upstairs BathroomDesign & Concept

Master Ensuite

6 tasks

Design & Concept

Master Ensuite — design brief and layout

Medium

Not Started

Hero bathroom. Freestanding bath, double vanity, walk-in frameless shower, separate WC. Heated floor. Premium finishes.

Master EnsuiteDesign & Concept

Construction & Fitout

Master Ensuite — procure tapware and fixtures

Medium

Not Started

Order all tapware: bath filler, rain shower, double basin mixers. Premium finish. Confirm lead times.

Master EnsuiteConstruction & Fitout

Master Ensuite — procure tiles

Medium

Not Started

Order premium tiles (marble/porcelain). Add 10% waste. Feature wall tiles may have longer lead time.

Master EnsuiteConstruction & Fitout

Master Ensuite — procure freestanding bath

Medium

Not Started

Order freestanding bath. Confirm: size fits, floor supports weight, waste position. Budget: A[price hidden]-4,000.

Master EnsuiteConstruction & Fitout

Master Ensuite — procure vanity + mirror

Medium

Not Started

Order double vanity and mirrors from selected supplier. Premium ensuite — allow longer lead time.

Master EnsuiteConstruction & Fitout

Finishes

Master Ensuite — snagging & defects

Low

Not Started

Allowance for 4-8 hours defect rectification @ [price hidden]/hr trade rate + materials. CONFIDENCE: 65/100 — Allowance-based. Actual snagging depends on quality of preceding trades. QUESTIONS: (1) Is this a builder responsibility under contract (defects liability period)? (2) Or a separate engagement for independent snagging inspector?
6 hrMaster EnsuiteFinishes

Kitchen

5 tasks

Pre-Construction Planning

Kitchen — full renovation + open plan living (builder quotes)

High

Not Started

MILESTONE: Umbrella task for entire kitchen renovation. 28 granular sub-tasks exist under Kitchen room. This task tracks the overall builder quoting process for the combined kitchen + open-plan scope.

No direct cost — planning/decision task. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
KitchenPre-Construction Planning

Design & Concept

Kitchen — complete design brief

Urgent

Not Started

Formal brief: island size, seating, storage zones, appliance locations, pantry type, waterfall ends, open shelving vs overheads.

KitchenDesign & Concept

Construction & Fitout

Kitchen — procure sink + tapware

Medium

Not Started

Order sink and tapware per selection. Confirm compatibility with benchtop cutout.

KitchenConstruction & Fitout

Kitchen — procure splashback materials

Medium

Not Started

Order splashback tiles or stone per design. Confirm colour match with benchtop.

KitchenConstruction & Fitout

Finishes

Kitchen snagging & defects walk-through

Medium

Not Started

Walk-through, punch list, minor remediation. Mix of general + skilled.

Allowance for 4-8 hours defect rectification @ [price hidden]/hr trade rate + materials. CONFIDENCE: 65/100 — Allowance-based. Actual snagging depends on quality of preceding trades. QUESTIONS: (1) Is this a builder responsibility under contract (defects liability period)? (2) Or a separate engagement for independent snagging inspector?
13 hrKitchenFinishes

Ground Floor Bathroom

4 tasks

Pre-Construction Planning

GF Bathroom — snagging & defects

Medium

Not Started

Allowance for 4-8 hours defect rectification @ [price hidden]/hr trade rate + materials. CONFIDENCE: 65/100 — Allowance-based. Actual snagging depends on quality of preceding trades. QUESTIONS: (1) Is this a builder responsibility under contract (defects liability period)? (2) Or a separate engagement for independent snagging inspector?
6 hrGround Floor BathroomPre-Construction Planning

Construction & Fitout

GF Bathroom — procure tiles

Medium

Not Started

Order floor and wall tiles per selection. Add 10% waste. Confirm delivery before tiler starts.

Ground Floor BathroomConstruction & Fitout

GF Bathroom — procure tapware and fixtures

Medium

Not Started

Order all tapware, shower, towel rails, toilet, accessories. Confirm finish matches FF Bathroom.

Ground Floor BathroomConstruction & Fitout

GF Bathroom — procure vanity + mirror

Medium

Not Started

Order vanity and mirror from selected supplier. Confirm lead time. Inspect on arrival.

Ground Floor BathroomConstruction & Fitout

Bedroom 2

2 tasks

Construction & Fitout

Extension fit-out — Bedroom 4 framing, insulation and plasterboard

High

Not Started

New Bed 4 in ground floor extension. Frame walls, insulate, plasterboard. Include window reveals and built-in robe framing.

Bedroom 2Construction & Fitout

Finishes

Bedroom 2 — snagging & defects

Low

Not Started

Allowance for 4-8 hours defect rectification @ [price hidden]/hr trade rate + materials. CONFIDENCE: 65/100 — Allowance-based. Actual snagging depends on quality of preceding trades. QUESTIONS: (1) Is this a builder responsibility under contract (defects liability period)? (2) Or a separate engagement for independent snagging inspector?
6 hrBedroom 2Finishes

Master Suite

2 tasks

Construction & Fitout

Extension fit-out — master suite framing and plasterboard (first floor)

High

Not Started

New master bedroom on first floor of extension. Frame walls, insulate, plasterboard. Include WIR framing. High ceilings if feasible.

Master SuiteConstruction & Fitout

Finishes

Master Suite — snagging & defects

Low

Not Started

Allowance for 4-8 hours defect rectification @ [price hidden]/hr trade rate + materials. CONFIDENCE: 65/100 — Allowance-based. Actual snagging depends on quality of preceding trades. QUESTIONS: (1) Is this a builder responsibility under contract (defects liability period)? (2) Or a separate engagement for independent snagging inspector?
6 hrMaster SuiteFinishes

Laundry

1 tasks

Finishes

Laundry — snagging & defects

Low

Not Started

Allowance for 4-8 hours defect rectification @ [price hidden]/hr trade rate + materials. CONFIDENCE: 65/100 — Allowance-based. Actual snagging depends on quality of preceding trades. QUESTIONS: (1) Is this a builder responsibility under contract (defects liability period)? (2) Or a separate engagement for independent snagging inspector?
5 hrLaundryFinishes

Study

1 tasks

Finishes

Study — snagging & defects

Low

Not Started

Allowance for 4-8 hours defect rectification @ [price hidden]/hr trade rate + materials. CONFIDENCE: 65/100 — Allowance-based. Actual snagging depends on quality of preceding trades. QUESTIONS: (1) Is this a builder responsibility under contract (defects liability period)? (2) Or a separate engagement for independent snagging inspector?
5 hrStudyFinishes

Library Shelves

1 tasks

Design & Concept

Library shelves — select timber species and finish

Medium

Not Started

Painted MDF (cleaner, cheaper) or natural timber (walnut, oak)? Stain vs paint, shelf depth, adjustable vs fixed.

Library ShelvesDesign & Concept

Foyer

1 tasks

Finishes

Foyer — snagging & defects

Low

Not Started

Allowance for 4-8 hours defect rectification @ [price hidden]/hr trade rate + materials. CONFIDENCE: 65/100 — Allowance-based. Actual snagging depends on quality of preceding trades. QUESTIONS: (1) Is this a builder responsibility under contract (defects liability period)? (2) Or a separate engagement for independent snagging inspector?
5 hrFoyerFinishes

Landscaping

1 tasks

Exterior & Landscaping

External snagging & defects — final walkthrough, touch-ups, clean

Low

Not Started

Allowance for 4-8 hours defect rectification @ [price hidden]/hr trade rate + materials. CONFIDENCE: 65/100 — Allowance-based. Actual snagging depends on quality of preceding trades. QUESTIONS: (1) Is this a builder responsibility under contract (defects liability period)? (2) Or a separate engagement for independent snagging inspector?
12 hrLandscapingExterior & Landscaping

Bedroom 3

1 tasks

Finishes

Bedroom 3 — snagging & defects

Low

Not Started

Allowance for 4-8 hours defect rectification @ [price hidden]/hr trade rate + materials. CONFIDENCE: 65/100 — Allowance-based. Actual snagging depends on quality of preceding trades. QUESTIONS: (1) Is this a builder responsibility under contract (defects liability period)? (2) Or a separate engagement for independent snagging inspector?
5 hrBedroom 3Finishes

Sequencing & Dependencies

Tasks that must be coordinated with other trades or completed in a specific order.

Kitchen snagging & defects walk-through

Depends on

Paint kitchen walls & ceilingKitchenFinish → Start
Install and connect all kitchen appliancesKitchenFinish → Start

Blocks

Facade — render / paint exterior wallsFacadeFinish → Start

GF Bathroom — snagging & defects

Depends on

GF Bathroom — plumbing rough-in (shower, vanity, WC, taps)Ground Floor BathroomFinish → Start
GF Bathroom — tapware, shower fittings, WC, accessoriesGround Floor BathroomFinish → Start
GF Bathroom — shower screenGround Floor BathroomFinish → Start
GF Bathroom — paint ceiling & non-tiled wallsGround Floor BathroomFinish → Start

FF Bathroom — snagging & defects

Depends on

FF Bathroom — install vanity + mirrorUpstairs BathroomFinish → Start
FF Bathroom — shower screen (supply & install)Upstairs BathroomFinish → Start
FF Bathroom — plumbing fit-off (install tapware, WC, bath, accessories)Upstairs BathroomFinish → Start
FF Bathroom — paint ceiling & non-tiled wallsUpstairs BathroomFinish → Start

Replace the driveway gate

Depends on

Demolish the existing garageDriveway & RampFinish → Start

Lounge — fireplace restoration (clean, re-point, mantel)

Blocks

Lounge — paint walls, ceiling, trimLoungeFinish → Start

External snagging & defects — final walkthrough, touch-ups, clean

Depends on

Paved areas — supply & lay pavers for paths, entertaining areaLandscapingFinish → Start
Outdoor path lighting — LED bollards, step lights, garden spotsLandscapingFinish → Start
Rear garden — garden bed preparation, soil, mulch & plantingLandscapingFinish → Start

Heritage & streetscape assessment (Ku-ring-gai council character requirements)

Blocks

Elevation studies — street presentation designFacadeFinish → Start

Facade — snagging & defects

Depends on

Facade — guttering & downpipesFacadeFinish → Start
Facade — front door replacementFacadeFinish → Start
Facade — render / paint exterior wallsFacadeFinish → Start

Lounge — Georgian trim (cornices, skirting, architraves, wainscoting)

Depends on

Lounge — HVAC rough-in (ducted zone)LoungeFinish → Start
Lounge — electrical rough-in (wall sconces, chandelier, skirting power, TV wall)LoungeFinish → Start

Blocks

Lounge — supply & install timber flooringLoungeFinish → Start

Lounge — snagging

Depends on

Lounge — supply & install chandelierLoungeFinish → Start
Lounge — window dressings (curtains / shutters)LoungeFinish → Start

Lounge — protect open fireplace during works

Blocks

Lounge — structural: open front wall to connect into 6m extensionLoungeFinish → Start

Master Ensuite — snagging & defects

Depends on

Master Ensuite — tapware, shower, WC, accessoriesMaster EnsuiteFinish → Start
Master Ensuite — paint non-tiled areasMaster EnsuiteFinish → Start
Master Ensuite — vanity + mirror procurement & installMaster EnsuiteFinish → Start
Master Ensuite — shower screenMaster EnsuiteFinish → Start

Interested in quoting?