Electrician

Scope of Works — 32a Archbold Road, Roseville NSW 2069

31

Tasks

19

Rooms

5

Phases

0%

Complete

Not Started: 31

Phase Coverage

Pre-Con

Design

Approvals

Demo

Build

Finishes

External

Summary by Room

RoomTasksDonePhases
Whole House60Design, Build, Finishes
Driveway & Ramp30Build
Kitchen20Pre-Con
Driveway Wall & New Staircase20Build
Master Suite20Build, Finishes
Dining20Build, Finishes
Lounge20Build, Finishes
Ground Floor Bathroom10Pre-Con
Upstairs Bathroom10Pre-Con
Library Shelves10Pre-Con
Decks10External
Bedroom 210Finishes
Foyer10Finishes
Bedroom 310Finishes
Master Ensuite10Build
Study10Finishes
Other10Build
Landscaping10External
Laundry10Finishes

Detailed Scope

Whole House

6 tasks

Design & Concept

Lighting design — ambient, task, accent per room

Medium

Not Started

Pendant over island, chandelier in lounge, downlights in bathrooms, step lights on stairs, garden bollards. Dimming zones. Switch plate positions. Smart home integration scope.

No direct cost — planning/decision task. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Whole HouseDesign & Concept

Construction & Fitout

Electrical — smart home wiring provisions

Low

Not Started

11 electrical points @ ~[price hidden]/pt. Includes GPO, switch, light point, cable. Sydney sparky rate [price hidden]/hr. CONFIDENCE: 60/100 — Electrical point counts estimated. Sydney sparky rates well-known ([price hidden]-110/hr). Point count is the main variable. QUESTIONS: (1) Exact number of power points, lights, and switches needed? (2) Any smart home / automation requirements? (3) Existing wiring — can it be reused or full rewire needed?
11 unitWhole HouseConstruction & Fitout

Electrical — data/comms cabling (Cat6 + TV points)

Medium

Not Started

~15 Cat6 data points + 4 TV/coax points + patch panel + comms rack. Cable [price hidden]/m x 200m + wall plates + labour. CONFIDENCE: 60/100 — Electrical point counts estimated. Sydney sparky rates well-known ([price hidden]-110/hr). Point count is the main variable. QUESTIONS: (1) Exact number of power points, lights, and switches needed? (2) Any smart home / automation requirements? (3) Existing wiring — can it be reused or full rewire needed?
19 unitWhole HouseConstruction & Fitout

Electrical — switchboard upgrade (3-phase if required)

High

Not Started

Upgrade to 3-phase 63A board. New enclosure, RCDs, MCBs, surge protection. Licensed electrician 1.5 days. CONFIDENCE: 60/100 — Electrical point counts estimated. Sydney sparky rates well-known ([price hidden]-110/hr). Point count is the main variable. QUESTIONS: (1) Exact number of power points, lights, and switches needed? (2) Any smart home / automation requirements? (3) Existing wiring — can it be reused or full rewire needed?
1 lotWhole HouseConstruction & Fitout

Electrical — smoke alarm compliance (interconnected)

High

Not Started

7 electrical points @ ~[price hidden]/pt. Includes GPO, switch, light point, cable. Sydney sparky rate [price hidden]/hr. CONFIDENCE: 60/100 — Electrical point counts estimated. Sydney sparky rates well-known ([price hidden]-110/hr). Point count is the main variable. QUESTIONS: (1) Exact number of power points, lights, and switches needed? (2) Any smart home / automation requirements? (3) Existing wiring — can it be reused or full rewire needed?
7 unitWhole HouseConstruction & Fitout

Finishes

Electrical — final test & tag

Medium

Not Started

4 electrical points @ ~[price hidden]/pt. Includes GPO, switch, light point, cable. Sydney sparky rate [price hidden]/hr. CONFIDENCE: 60/100 — Electrical point counts estimated. Sydney sparky rates well-known ([price hidden]-110/hr). Point count is the main variable. QUESTIONS: (1) Exact number of power points, lights, and switches needed? (2) Any smart home / automation requirements? (3) Existing wiring — can it be reused or full rewire needed?
4 unitWhole HouseFinishes

Driveway & Ramp

3 tasks

Construction & Fitout

Run power to the lower driveway lights

Medium

Not Started

Run a feed to the low-level lights set within the driveway.

Driveway & RampConstruction & Fitout

Electrical parts — conduit, cable, fittings

Medium

Not Started

Driveway & RampConstruction & Fitout

Electrician labour — trench, wire & install

Medium

Not Started

Combined with other site electrical works
Driveway & RampConstruction & Fitout

Kitchen

2 tasks

Pre-Construction Planning

Electrical rough-in (island power, pendants, downlights, appliance circuits)

High

Not Started

Licensed sparky, 3 days. Cable, fittings, board upgrades if needed.

Kitchen electrical rough-in — ~28 points total: Island: 4x double GPO (8 points for appliances/charging) — in floor or through island Perimeter: 4x double GPO above bench height Dedicated circuits: oven (32A), cooktop (32A if induction), dishwasher Lighting: 6x LED downlights (IC-rated, dimmable) + 3x pendant drops over island Switches: 3x dimmer switches + 2x standard switches Cost per point: cable run [price hidden] + fitting/plate [price hidden] + labour 0.75hr @ [price hidden]/hr = ~[price hidden]-[price hidden]/pt depending on complexity. Average [price hidden]/point for kitchen (higher than standard due to dedicated circuits and island cable routing). QTY: 28 points @ [price hidden]/pt = [price hidden] ≈ [price hidden]. CONFIDENCE: 65/100 — Point count based on typical modern kitchen. Actual count depends on final kitchen layout. Island power routing (through slab or benchtop) affects cost. Induction cooktop needs 32A circuit. QUESTIONS: (1) How many GPOs on island — 4 doubles or 2 doubles? (2) Pendant style — hard-wired or track? (3) Induction cooktop requiring dedicated 32A circuit? (4) Under-cabinet LED strip lighting wanted? (5) Smart switches/dimmers?
28 unitKitchenPre-Construction Planning

Kitchen — electrical upgrade (new circuits, downlights)

High

Not Started

Update kitchen electrical — new circuits, rangehood vent, additional power points, LED downlights in open plan area.

No direct cost — planning/decision task. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
KitchenPre-Construction Planning

Driveway Wall & New Staircase

2 tasks

Construction & Fitout

Install step lights in staircase treads

Medium

Not Started

Electrician to run cable during staircase construction (before pour). Recessed LED step lights in stair risers. IP65 minimum. Warm white (3000K). Connect to lighting circuit with timer/sensor. Conduit in concrete for future maintenance access.

Driveway Wall & New StaircaseConstruction & Fitout

Install retaining wall feature lighting

Low

Not Started

Electrician to install wall-wash or uplight fixtures at base of retaining wall. LED, warm white, IP65. Spacing per lighting design. Conduit and cable during wall construction. Connect to landscape lighting circuit.

Driveway Wall & New StaircaseConstruction & Fitout

Master Suite

2 tasks

Construction & Fitout

Extension fit-out — first floor electrical and lighting rough-in

High

Not Started

All electrical for first floor rooms: master suite, ensuite, hallway. Lighting circuits, power points, data points per lighting design.

Master SuiteConstruction & Fitout

Finishes

Master Suite — lighting (downlights, bedside, feature)

Medium

Not Started

5 light fittings avg [price hidden]/unit supply + [price hidden]/unit install. Mid-range LED downlights / pendants. CONFIDENCE: 55/100 — LED downlight pricing is stable. Feature pendants/chandeliers vary widely ([price hidden]-[price hidden]). QUESTIONS: (1) Feature vs standard lighting? (2) Any specific fixtures already selected? (3) Dimmer switches required?
5 unitMaster SuiteFinishes

Dining

2 tasks

Construction & Fitout

Dining — electrical rough-in (pendant over dining table, wall sconces, downlights)

Medium

Not Started

16 electrical points @ ~[price hidden]/pt. Includes GPO, switch, light point, cable. Sydney sparky rate [price hidden]/hr. CONFIDENCE: 60/100 — Electrical point counts estimated. Sydney sparky rates well-known ([price hidden]-110/hr). Point count is the main variable. QUESTIONS: (1) Exact number of power points, lights, and switches needed? (2) Any smart home / automation requirements? (3) Existing wiring — can it be reused or full rewire needed?
16 unitDiningConstruction & Fitout

Finishes

Dining — supply & install pendant light fitting

Low

Not Started

Owner-supplied

Feature pendant/chandelier supply + electrician install. Mid-range fitting. CONFIDENCE: 55/100 — LED downlight pricing is stable. Feature pendants/chandeliers vary widely ([price hidden]-[price hidden]). QUESTIONS: (1) Feature vs standard lighting? (2) Any specific fixtures already selected? (3) Dimmer switches required?
1 unitDiningFinishes

Lounge

2 tasks

Construction & Fitout

Lounge — electrical rough-in (wall sconces, chandelier, skirting power, TV wall)

Medium

Not Started

~18 points: 6 wall sconces, 1 chandelier point, 4 skirting GPO, 2 data, 3 switches, 2 TV/AV. [price hidden]/pt. CONFIDENCE: 60/100 — Electrical point counts estimated. Sydney sparky rates well-known ([price hidden]-110/hr). Point count is the main variable. QUESTIONS: (1) Exact number of power points, lights, and switches needed? (2) Any smart home / automation requirements? (3) Existing wiring — can it be reused or full rewire needed?
18 unitLoungeConstruction & Fitout

Finishes

Lounge — supply & install chandelier

Medium

Not Started

Owner-supplied

Feature pendant/chandelier supply + electrician install. Mid-range fitting. CONFIDENCE: 55/100 — LED downlight pricing is stable. Feature pendants/chandeliers vary widely ([price hidden]-[price hidden]). QUESTIONS: (1) Feature vs standard lighting? (2) Any specific fixtures already selected? (3) Dimmer switches required?
1 unitLoungeFinishes

Ground Floor Bathroom

1 tasks

Pre-Construction Planning

GF Bathroom — electrical rough-in (downlights, exhaust fan, heated towel rail, mirror)

High

Not Started

12 electrical points @ ~[price hidden]/pt. Includes GPO, switch, light point, cable. Sydney sparky rate [price hidden]/hr. CONFIDENCE: 60/100 — Electrical point counts estimated. Sydney sparky rates well-known ([price hidden]-110/hr). Point count is the main variable. QUESTIONS: (1) Exact number of power points, lights, and switches needed? (2) Any smart home / automation requirements? (3) Existing wiring — can it be reused or full rewire needed?
12 unitGround Floor BathroomPre-Construction Planning

Upstairs Bathroom

1 tasks

Pre-Construction Planning

FF Bathroom — electrical rough-in (downlights, exhaust, heated rail, mirror)

High

Not Started

13 electrical points @ ~[price hidden]/pt. Includes GPO, switch, light point, cable. Sydney sparky rate [price hidden]/hr. CONFIDENCE: 60/100 — Electrical point counts estimated. Sydney sparky rates well-known ([price hidden]-110/hr). Point count is the main variable. QUESTIONS: (1) Exact number of power points, lights, and switches needed? (2) Any smart home / automation requirements? (3) Existing wiring — can it be reused or full rewire needed?

Scope of works

  1. 1
    Set out lights, exhaust, heated rail, mirror, GPOsPositions per plan; IP zones observed around shower/bath per AS/NZS 3000.
  2. 2
    Run cabling + noggins/backingBacking blocks for heated rail & mirror; cabling clear of wet zones.
  3. 3
    Duct exhaust fan to outside airRigid/semi-rigid duct to external vent — NOT into roof cavity.
  4. 4
    RCD-protected circuits + complianceAll circuits RCD protected; Certificate of Compliance issued.
13 unitUpstairs BathroomPre-Construction Planning

Library Shelves

1 tasks

Pre-Construction Planning

Library shelves — integrated lighting (optional)

Low

Not Started

Picture lights or LED strip integration

3 light fittings avg [price hidden]/unit supply + [price hidden]/unit install. Mid-range LED downlights / pendants. CONFIDENCE: 50/100 — Joinery is bespoke — costs depend on material, complexity, and finish. Must be quoted by cabinetmaker. QUESTIONS: (1) Design/drawings complete? (2) Material — MDF, ply, solid timber? (3) Finish — 2-pac spray, laminate, or natural? (4) Hardware — Blum/Hettich soft-close?
3 unitLibrary ShelvesPre-Construction Planning

Decks

1 tasks

Exterior & Landscaping

Entertaining deck lighting — festoon/string lights + deck downlights

Low

Not Started

6 light fittings avg [price hidden]/unit supply + [price hidden]/unit install. Mid-range LED downlights / pendants. CONFIDENCE: 55/100 — LED downlight pricing is stable. Feature pendants/chandeliers vary widely ([price hidden]-[price hidden]). QUESTIONS: (1) Feature vs standard lighting? (2) Any specific fixtures already selected? (3) Dimmer switches required?
6 unitDecksExterior & Landscaping

Bedroom 2

1 tasks

Finishes

Bedroom 2 — lighting (downlights + bedside)

Low

Not Started

3 light fittings avg [price hidden]/unit supply + [price hidden]/unit install. Mid-range LED downlights / pendants. CONFIDENCE: 55/100 — LED downlight pricing is stable. Feature pendants/chandeliers vary widely ([price hidden]-[price hidden]). QUESTIONS: (1) Feature vs standard lighting? (2) Any specific fixtures already selected? (3) Dimmer switches required?
3 unitBedroom 2Finishes

Foyer

1 tasks

Finishes

Foyer — lighting (entry pendant + hall downlights)

Medium

Not Started

6 light fittings avg [price hidden]/unit supply + [price hidden]/unit install. Mid-range LED downlights / pendants. CONFIDENCE: 55/100 — LED downlight pricing is stable. Feature pendants/chandeliers vary widely ([price hidden]-[price hidden]). QUESTIONS: (1) Feature vs standard lighting? (2) Any specific fixtures already selected? (3) Dimmer switches required?
6 unitFoyerFinishes

Bedroom 3

1 tasks

Finishes

Bedroom 3 — lighting

Low

Not Started

3 light fittings avg [price hidden]/unit supply + [price hidden]/unit install. Mid-range LED downlights / pendants. CONFIDENCE: 55/100 — LED downlight pricing is stable. Feature pendants/chandeliers vary widely ([price hidden]-[price hidden]). QUESTIONS: (1) Feature vs standard lighting? (2) Any specific fixtures already selected? (3) Dimmer switches required?
3 unitBedroom 3Finishes

Master Ensuite

1 tasks

Construction & Fitout

Master Ensuite — electrical rough-in (downlights, exhaust, heated rail, mirror)

High

Not Started

14 electrical points @ ~[price hidden]/pt. Includes GPO, switch, light point, cable. Sydney sparky rate [price hidden]/hr. CONFIDENCE: 60/100 — Electrical point counts estimated. Sydney sparky rates well-known ([price hidden]-110/hr). Point count is the main variable. QUESTIONS: (1) Exact number of power points, lights, and switches needed? (2) Any smart home / automation requirements? (3) Existing wiring — can it be reused or full rewire needed?
14 unitMaster EnsuiteConstruction & Fitout

Study

1 tasks

Finishes

Study — electrical (data points, power, lighting)

Medium

Not Started

10 electrical points @ ~[price hidden]/pt. Includes GPO, switch, light point, cable. Sydney sparky rate [price hidden]/hr. CONFIDENCE: 60/100 — Electrical point counts estimated. Sydney sparky rates well-known ([price hidden]-110/hr). Point count is the main variable. QUESTIONS: (1) Exact number of power points, lights, and switches needed? (2) Any smart home / automation requirements? (3) Existing wiring — can it be reused or full rewire needed?
10 unitStudyFinishes

Other

1 tasks

Construction & Fitout

Underground garage — drainage, ventilation and electrical

High

Not Started

Stormwater drainage at entry and internal sump pump. Mechanical ventilation (AS1668.2 for enclosed car parks). Lighting, power for EV charger, auto door wiring.

Construction & Fitout

Landscaping

1 tasks

Exterior & Landscaping

Outdoor path lighting — LED bollards, step lights, garden spots

Low

Not Started

10 LED bollard/spike lights [price hidden]/ea + transformer [price hidden] + 50m low voltage cable [price hidden] + electrician 1 day. CONFIDENCE: 55/100 — LED downlight pricing is stable. Feature pendants/chandeliers vary widely ([price hidden]-[price hidden]). QUESTIONS: (1) Feature vs standard lighting? (2) Any specific fixtures already selected? (3) Dimmer switches required?
10 unitLandscapingExterior & Landscaping

Laundry

1 tasks

Finishes

Laundry — electrical (power, lighting)

Medium

Not Started

7 electrical points @ ~[price hidden]/pt. Includes GPO, switch, light point, cable. Sydney sparky rate [price hidden]/hr. CONFIDENCE: 60/100 — Electrical point counts estimated. Sydney sparky rates well-known ([price hidden]-110/hr). Point count is the main variable. QUESTIONS: (1) Exact number of power points, lights, and switches needed? (2) Any smart home / automation requirements? (3) Existing wiring — can it be reused or full rewire needed?
7 unitLaundryFinishes

Sequencing & Dependencies

Tasks that must be coordinated with other trades or completed in a specific order.

Electrical rough-in (island power, pendants, downlights, appliance circuits)

Depends on

Demolish existing kitchen (cabinetry, benchtops, splashback, appliances)KitchenFinish → Start

Blocks

Kitchen cabinetry supply & install (shaker, base + overhead + pantry)KitchenFinish → Start

GF Bathroom — electrical rough-in (downlights, exhaust fan, heated towel rail, mirror)

Depends on

GF Bathroom — strip-out (tiles, fittings, vanity, shower, WC)Ground Floor BathroomFinish → Start

Blocks

GF Bathroom — waterproofing (floor + walls to 1.8m)Ground Floor BathroomFinish → Start

FF Bathroom — electrical rough-in (downlights, exhaust, heated rail, mirror)

Depends on

FF Bathroom — strip-out & waste removalUpstairs BathroomFinish → Start

Blocks

FF Bathroom — waterproofing (floor + walls + wet area)Upstairs BathroomFinish → Start

Electrical — final test & tag

Depends on

Electrical — smoke alarm compliance (interconnected)Whole HouseFinish → Start
HVAC — commissioning & balancingWhole HouseFinish → Start
Electrical — data/comms cabling (Cat6 + TV points)Whole HouseFinish → Start

Electrical — data/comms cabling (Cat6 + TV points)

Depends on

Electrical — switchboard upgrade (3-phase if required)Whole HouseStart → Start

Blocks

Electrical — final test & tagWhole HouseFinish → Start

Lounge — supply & install chandelier

Depends on

Lounge — paint walls, ceiling, trimLoungeFinish → Start

Blocks

Lounge — snaggingLoungeFinish → Start

Electrical — switchboard upgrade (3-phase if required)

Blocks

Electrical — smoke alarm compliance (interconnected)Whole HouseFinish → Start
Electrical — data/comms cabling (Cat6 + TV points)Whole HouseStart → Start

Electrical — smoke alarm compliance (interconnected)

Depends on

Electrical — switchboard upgrade (3-phase if required)Whole HouseFinish → Start

Blocks

Electrical — final test & tagWhole HouseFinish → Start

Master Ensuite — electrical rough-in (downlights, exhaust, heated rail, mirror)

Depends on

Master Ensuite — strip-out existingMaster EnsuiteFinish → Start

Blocks

Master Ensuite — waterproofing (floor + walls)Master EnsuiteFinish → Start

Lounge — electrical rough-in (wall sconces, chandelier, skirting power, TV wall)

Depends on

Lounge — structural: open front wall to connect into 6m extensionLoungeFinish → Start

Blocks

Lounge — Georgian trim (cornices, skirting, architraves, wainscoting)LoungeFinish → Start

Outdoor path lighting — LED bollards, step lights, garden spots

Depends on

Paved areas — supply & lay pavers for paths, entertaining areaLandscapingStart → Start

Blocks

External snagging & defects — final walkthrough, touch-ups, cleanLandscapingFinish → Start