Electrician
Scope of Works — 32a Archbold Road, Roseville NSW 2069
31
Tasks
19
Rooms
5
Phases
0%
Complete
Phase Coverage
Pre-Con
Design
Approvals
Demo
Build
Finishes
External
Summary by Room
| Room | Tasks | Done | Phases |
|---|---|---|---|
| Whole House | 6 | 0 | Design, Build, Finishes |
| Driveway & Ramp | 3 | 0 | Build |
| Kitchen | 2 | 0 | Pre-Con |
| Driveway Wall & New Staircase | 2 | 0 | Build |
| Master Suite | 2 | 0 | Build, Finishes |
| Dining | 2 | 0 | Build, Finishes |
| Lounge | 2 | 0 | Build, Finishes |
| Ground Floor Bathroom | 1 | 0 | Pre-Con |
| Upstairs Bathroom | 1 | 0 | Pre-Con |
| Library Shelves | 1 | 0 | Pre-Con |
| Decks | 1 | 0 | External |
| Bedroom 2 | 1 | 0 | Finishes |
| Foyer | 1 | 0 | Finishes |
| Bedroom 3 | 1 | 0 | Finishes |
| Master Ensuite | 1 | 0 | Build |
| Study | 1 | 0 | Finishes |
| Other | 1 | 0 | Build |
| Landscaping | 1 | 0 | External |
| Laundry | 1 | 0 | Finishes |
Detailed Scope
Whole House
6 tasksDesign & Concept
Lighting design — ambient, task, accent per room
MediumNot Started
Pendant over island, chandelier in lounge, downlights in bathrooms, step lights on stairs, garden bollards. Dimming zones. Switch plate positions. Smart home integration scope.
Construction & Fitout
Electrical — smart home wiring provisions
LowNot Started
Electrical — data/comms cabling (Cat6 + TV points)
MediumNot Started
Electrical — switchboard upgrade (3-phase if required)
HighNot Started
Electrical — smoke alarm compliance (interconnected)
HighNot Started
Finishes
Electrical — final test & tag
MediumNot Started
Driveway & Ramp
3 tasksConstruction & Fitout
Run power to the lower driveway lights
MediumNot Started
Run a feed to the low-level lights set within the driveway.
Electrical parts — conduit, cable, fittings
MediumNot Started
Electrician labour — trench, wire & install
MediumNot Started
Kitchen
2 tasksPre-Construction Planning
Electrical rough-in (island power, pendants, downlights, appliance circuits)
HighNot Started
Licensed sparky, 3 days. Cable, fittings, board upgrades if needed.
Kitchen — electrical upgrade (new circuits, downlights)
HighNot Started
Update kitchen electrical — new circuits, rangehood vent, additional power points, LED downlights in open plan area.
Driveway Wall & New Staircase
2 tasksConstruction & Fitout
Install step lights in staircase treads
MediumNot Started
Electrician to run cable during staircase construction (before pour). Recessed LED step lights in stair risers. IP65 minimum. Warm white (3000K). Connect to lighting circuit with timer/sensor. Conduit in concrete for future maintenance access.
Install retaining wall feature lighting
LowNot Started
Electrician to install wall-wash or uplight fixtures at base of retaining wall. LED, warm white, IP65. Spacing per lighting design. Conduit and cable during wall construction. Connect to landscape lighting circuit.
Master Suite
2 tasksConstruction & Fitout
Extension fit-out — first floor electrical and lighting rough-in
HighNot Started
All electrical for first floor rooms: master suite, ensuite, hallway. Lighting circuits, power points, data points per lighting design.
Finishes
Master Suite — lighting (downlights, bedside, feature)
MediumNot Started
Dining
2 tasksConstruction & Fitout
Dining — electrical rough-in (pendant over dining table, wall sconces, downlights)
MediumNot Started
Finishes
Dining — supply & install pendant light fitting
LowNot Started
Owner-supplied
Lounge
2 tasksConstruction & Fitout
Lounge — electrical rough-in (wall sconces, chandelier, skirting power, TV wall)
MediumNot Started
Finishes
Lounge — supply & install chandelier
MediumNot Started
Owner-supplied
Ground Floor Bathroom
1 tasksPre-Construction Planning
GF Bathroom — electrical rough-in (downlights, exhaust fan, heated towel rail, mirror)
HighNot Started
Upstairs Bathroom
1 tasksPre-Construction Planning
FF Bathroom — electrical rough-in (downlights, exhaust, heated rail, mirror)
HighNot Started
Scope of works
- 1Set out lights, exhaust, heated rail, mirror, GPOs — Positions per plan; IP zones observed around shower/bath per AS/NZS 3000.
- 2Run cabling + noggins/backing — Backing blocks for heated rail & mirror; cabling clear of wet zones.
- 3Duct exhaust fan to outside air — Rigid/semi-rigid duct to external vent — NOT into roof cavity.
- 4RCD-protected circuits + compliance — All circuits RCD protected; Certificate of Compliance issued.
Library Shelves
1 tasksPre-Construction Planning
Library shelves — integrated lighting (optional)
LowNot Started
Picture lights or LED strip integration
Decks
1 tasksExterior & Landscaping
Entertaining deck lighting — festoon/string lights + deck downlights
LowNot Started
Bedroom 2
1 tasksFinishes
Bedroom 2 — lighting (downlights + bedside)
LowNot Started
Foyer
1 tasksFinishes
Foyer — lighting (entry pendant + hall downlights)
MediumNot Started
Bedroom 3
1 tasksFinishes
Bedroom 3 — lighting
LowNot Started
Master Ensuite
1 tasksConstruction & Fitout
Master Ensuite — electrical rough-in (downlights, exhaust, heated rail, mirror)
HighNot Started
Study
1 tasksFinishes
Study — electrical (data points, power, lighting)
MediumNot Started
Other
1 tasksConstruction & Fitout
Underground garage — drainage, ventilation and electrical
HighNot Started
Stormwater drainage at entry and internal sump pump. Mechanical ventilation (AS1668.2 for enclosed car parks). Lighting, power for EV charger, auto door wiring.
Landscaping
1 tasksExterior & Landscaping
Outdoor path lighting — LED bollards, step lights, garden spots
LowNot Started
Laundry
1 tasksFinishes
Laundry — electrical (power, lighting)
MediumNot Started
Sequencing & Dependencies
Tasks that must be coordinated with other trades or completed in a specific order.
Electrical rough-in (island power, pendants, downlights, appliance circuits)
Depends on
Blocks
GF Bathroom — electrical rough-in (downlights, exhaust fan, heated towel rail, mirror)
Depends on
Blocks
FF Bathroom — electrical rough-in (downlights, exhaust, heated rail, mirror)
Depends on
Blocks
Electrical — final test & tag
Depends on
Electrical — data/comms cabling (Cat6 + TV points)
Depends on
Blocks
Lounge — supply & install chandelier
Depends on
Blocks
Electrical — switchboard upgrade (3-phase if required)
Blocks
Electrical — smoke alarm compliance (interconnected)
Depends on
Blocks
Master Ensuite — electrical rough-in (downlights, exhaust, heated rail, mirror)
Depends on
Blocks
Lounge — electrical rough-in (wall sconces, chandelier, skirting power, TV wall)
Depends on
Blocks
Outdoor path lighting — LED bollards, step lights, garden spots
Depends on
Blocks
Interested in quoting?
Submit your details and availability to be considered for the Electrician package.