Demo / Earthworks
Scope of Works — 32a Archbold Road, Roseville NSW 2069
14
Tasks
5
Rooms
3
Phases
0%
Complete
Phase Coverage
Pre-Con
Design
Approvals
Demo
Build
Finishes
External
Summary by Room
| Room | Tasks | Done | Phases |
|---|---|---|---|
| Driveway & Ramp | 7 | 0 | Pre-Con |
| Driveway Wall & New Staircase | 4 | 0 | Demo, Build |
| Kitchen | 1 | 0 | Pre-Con |
| Master Ensuite | 1 | 0 | Demo |
| Dining | 1 | 0 | Demo |
Detailed Scope
Driveway & Ramp
7 tasksPre-Construction Planning
Demolish the existing garage
HighIn Progress
Self-managed: digger + operator @ [price hidden]/day, 2 days total shared with lower-garden excavation. Old gate comes off during demo.
Tear up the existing concrete driveway
HighNot Started
1 day of digger + operator time. Waste into skips / recycler pending the recycling-viability check.
Excavate the lower garden
HighNot Started
Day 2 of the 2-day digger hire. Sub-base import TBC after recycling check.
Digger + operator — day 1 of 2: demolish garage
HighIn Progress
Digger + operator rental. Add [price hidden]/day if jackhammer bit required (likely for garage slab). Demo guy estimates garage demo + excavation = 2 days total.
Digger + operator — 1 day: rip up driveway concrete
HighNot Started
Jackhammer bit hire (if required)
MediumNot Started
[price hidden]/day digger attachment — needed for breaking concrete.
Digger + operator — day 2 of 2: excavate lower garden
HighNot Started
Second day of the 2-day digger hire (garage demo + excavation per demo guy's estimate).
Driveway Wall & New Staircase
4 tasksDemolition & Strip-out
Demolish existing retaining wall
HighNot Started
Demolition contractor. Method depends on wall material. Concrete: use excavator with hydraulic hammer. Timber: dismantle by hand. Remove all rubble to skip bin. Temp shore any exposed soil face. Make safe for next stage.
Remove existing hillside staircase
HighNot Started
Remove existing steps (concrete/timber). Clear rubble. Grade and compact soil where new staircase will be built. Maintain temporary access if possible during construction.
Construction & Fitout
Excavate for new retaining wall footings
HighNot Started
Excavation per structural engineer spec. Footing width and depth as per drawings. Allow for rock hammering if sandstone encountered (common in Roseville). Level and compact base. Inspect before reinforcing.
Backfill behind retaining wall in compacted layers
MediumNot Started
Backfill in max 300mm layers, compact each layer to 95% Modified Proctor. Use clean fill (no organics). Grade top surface for parking area with 2% fall away from wall. Final level to match driveway design.
Kitchen
1 tasksPre-Construction Planning
Demolish dividing wall between kitchen and dining
HighNot Started
REVISED: 20 gen + 8 skilled hrs + dust containment + bin. Load-bearing wall removal.
Master Ensuite
1 tasksDemolition & Strip-out
Master Ensuite — strip-out existing
HighNot Started
Dining
1 tasksDemolition & Strip-out
Dining — demolish finishes, protect floor if retained
MediumNot Started
MOVED TO EXTENSION PHASE - to be deleted
Sequencing & Dependencies
Tasks that must be coordinated with other trades or completed in a specific order.
Demolish dividing wall between kitchen and dining
Depends on
Blocks
Demolish the existing garage
Blocks
Master Ensuite — strip-out existing
Blocks
Interested in quoting?
Submit your details and availability to be considered for the Demo / Earthworks package.