Concreter
Scope of Works — 32a Archbold Road, Roseville NSW 2069
11
Tasks
2
Rooms
1
Phases
0%
Complete
Phase Coverage
Pre-Con
Design
Approvals
Demo
Build
Finishes
External
Summary by Room
| Room | Tasks | Done | Phases |
|---|---|---|---|
| Other | 6 | 0 | Build |
| Driveway Wall & New Staircase | 5 | 0 | Build |
Detailed Scope
Other
6 tasksConstruction & Fitout
Extension — excavate and pour strip footings (63m²)
HighNot Started
Excavate to engineer's spec depth. Formwork, reinforcing steel, concrete pour. Allow for rock if encountered (Roseville ridge). Inspections: footing before pour.
Extension — ground floor slab pour (63m²)
HighNot Started
Slab on ground with mesh reinforcing. Plumbing rough-in and piers set before pour. Inspect: pre-slab. Cure minimum 7 days before loading.
Underground garage — reinforced concrete retaining walls
HighNot Started
Reinforced concrete walls on three sides (cut faces). Engineer-designed. Formwork, reo, pour. Minimum 200mm thick. Control joints per engineer.
Underground garage — floor slab and roof slab pour
HighNot Started
Floor slab: 150mm reinforced on compacted base. Roof slab: 200mm+ reinforced (must support lawn/garden above). Falls to drainage. Cure before backfill.
Underground garage — driveway ramp and entry
HighNot Started
Ramp from street level to garage entry. Max 1:5 gradient. Non-slip surface. Drainage grate at base. Auto garage door. Retaining walls either side of ramp.
Post-extension — underground garage: hillside cut + concrete structure
LowNot Started
MILESTONE: Now tracked via 6 sub-tasks (excavation, retaining walls, slabs, waterproofing, services, ramp). Check sub-tasks for progress.
Driveway Wall & New Staircase
5 tasksConstruction & Fitout
Install staircase handrail and balustrade
MediumNot Started
Handrail must comply with BCA: 865-1000mm height, graspable profile, no climbable elements. Material per design selection. Fix to staircase structure with chemical anchors. Include intermediate posts if required.
Install reinforcing steel for retaining wall footings
HighNot Started
Steel fixer to install reo per structural engineer schedule. Starter bars projecting up for wall connection. Formwork for footing pour. Inspect: reo coverage, bar sizes, spacing, laps, chair heights. Engineer inspection before pour.
Pour retaining wall footings
HighNot Started
Concrete pump or direct pour depending on access. Vibrate to remove air pockets. Level top to formwork. Cure minimum 7 days before wall construction begins. Protect from rain during cure.
Construct retaining wall to engineer's design
HighNot Started
Main construction phase. Method per structural engineer design: formwork and poured concrete, or concrete block with core-filled reo. Wall face finish: exposed aggregate, rendered, or stone-faced cladding per design selection. Control joints per engineer spec.
Form and pour concrete staircase treads and landings
HighNot Started
Formwork for each tread (riser 150-190mm, going 250-300mm per BCA). Landing every 18 risers. Reinforcing per engineer. Non-slip broom finish or exposed aggregate. Edge nosings. Cure before removing forms.