← All tradesPrint / PDF

Concreter

Scope of Works — 32a Archbold Road, Roseville NSW 2069

11

Tasks

2

Rooms

1

Phases

0%

Complete

Not Started: 11

Phase Coverage

Pre-Con

Design

Approvals

Demo

Build

Finishes

External

Summary by Room

RoomTasksDonePhases
Other60Build
Driveway Wall & New Staircase50Build

Detailed Scope

Other

6 tasks

Construction & Fitout

Extension — excavate and pour strip footings (63m²)

High

Not Started

Excavate to engineer's spec depth. Formwork, reinforcing steel, concrete pour. Allow for rock if encountered (Roseville ridge). Inspections: footing before pour.

Construction & Fitout

Extension — ground floor slab pour (63m²)

High

Not Started

Slab on ground with mesh reinforcing. Plumbing rough-in and piers set before pour. Inspect: pre-slab. Cure minimum 7 days before loading.

Construction & Fitout

Underground garage — reinforced concrete retaining walls

High

Not Started

Reinforced concrete walls on three sides (cut faces). Engineer-designed. Formwork, reo, pour. Minimum 200mm thick. Control joints per engineer.

Construction & Fitout

Underground garage — floor slab and roof slab pour

High

Not Started

Floor slab: 150mm reinforced on compacted base. Roof slab: 200mm+ reinforced (must support lawn/garden above). Falls to drainage. Cure before backfill.

Construction & Fitout

Underground garage — driveway ramp and entry

High

Not Started

Ramp from street level to garage entry. Max 1:5 gradient. Non-slip surface. Drainage grate at base. Auto garage door. Retaining walls either side of ramp.

Construction & Fitout

Post-extension — underground garage: hillside cut + concrete structure

Low

Not Started

MILESTONE: Now tracked via 6 sub-tasks (excavation, retaining walls, slabs, waterproofing, services, ramp). Check sub-tasks for progress.

No direct cost — planning/decision task. CONFIDENCE: 90/100 — No direct cost. Planning/decision task. QUESTIONS: None — owner labour only.
Construction & Fitout

Driveway Wall & New Staircase

5 tasks

Construction & Fitout

Install staircase handrail and balustrade

Medium

Not Started

Handrail must comply with BCA: 865-1000mm height, graspable profile, no climbable elements. Material per design selection. Fix to staircase structure with chemical anchors. Include intermediate posts if required.

Driveway Wall & New StaircaseConstruction & Fitout

Install reinforcing steel for retaining wall footings

High

Not Started

Steel fixer to install reo per structural engineer schedule. Starter bars projecting up for wall connection. Formwork for footing pour. Inspect: reo coverage, bar sizes, spacing, laps, chair heights. Engineer inspection before pour.

Driveway Wall & New StaircaseConstruction & Fitout

Pour retaining wall footings

High

Not Started

Concrete pump or direct pour depending on access. Vibrate to remove air pockets. Level top to formwork. Cure minimum 7 days before wall construction begins. Protect from rain during cure.

Driveway Wall & New StaircaseConstruction & Fitout

Construct retaining wall to engineer's design

High

Not Started

Main construction phase. Method per structural engineer design: formwork and poured concrete, or concrete block with core-filled reo. Wall face finish: exposed aggregate, rendered, or stone-faced cladding per design selection. Control joints per engineer spec.

Driveway Wall & New StaircaseConstruction & Fitout

Form and pour concrete staircase treads and landings

High

Not Started

Formwork for each tread (riser 150-190mm, going 250-300mm per BCA). Landing every 18 risers. Reinforcing per engineer. Non-slip broom finish or exposed aggregate. Edge nosings. Cure before removing forms.

Driveway Wall & New StaircaseConstruction & Fitout

Interested in quoting?

Submit your details and availability to be considered for the Concreter package.